General Exception Notice - Broadmarsh Car Park Development Contract Extension - 12/11/2020  (12/11/2020 to 20/11/2020, Leader's Key Decision - Notice)

Plan items
No. Item

1.

Broadmarsh Car Park Development Contract Extension - Key Decision New!

Decision maker:  Leader of the Council

Decision due:   Not before 20th Nov 2020

Lead officer:  Steve Dickens

Notice of proposed decision first published: 12/11/2020

This decision will be taken under urgency procedures.

Reason for urgency:
The decision could not be included on a 28-Day Notice because the development requires items that have a long lead time for supply, but these items cannot be ordered until an appropriate contract extension is in place. Each week taken to agree the contract extension delays the completion date for the development and increases the costs, so it is important to implement the decision as quickly as possible.

Anticipated restriction: Open  -